Contract-issuingparty:FoshanGas Projectname:hottap&linestopon16-inchgaspipelineforpipesectionreplacement Projectlocation:GuangdongProvince Constructiondate:fromJan.26,2018toJan.31,2018 Workingcontent:

Contract-issuing party: Foshan Gas
 
Project name: hot tap & line stop on 16-inch gas pipeline for pipe section replacement
 
Project location: Guangdong Province
 
Construction date: from Jan. 26, 2018 to Jan.31, 2018
 
Working content: hot tap &line stop on 16-inch gas pipeline, Nos:1
 
Design pressure: 16bar
 
Operating pressure: less than 16bar

 

 

 

 

 

 

 

 

 

 